Self driven, assertive and dedicated Cost Controller bringing 8 years experience working with Multimillion Infrastructure, Industrial and Building Projects. With proven leadership and success in leading teams in achieving cost control goals in construction projects. Highly organized and systematic with in depth understanding of construction projects.
Certificate in WinQs
Certificate in Quickbooks
PROJECTS HANDLED
Project Vegetable Oil Storage Facility in Mombasa and Nairobi of capacity 35,000 metric tonnes. Project Value Kshs. 1.3Billion. Status; Ongoing 50% complete
Key role; Cost Controller in charge of all matters related to cost management, budget review, cost reporting and preparation of cashflow project, Preparation of Cost Estimates, Preparation of Working Budget and tracking the same, Preparation Project Budget both local and import works. Budget presentation,Preparation of Cost management documents
Proposed Value Chain Projects which comprised of Grain Terminal of Capacity 134,000metric tonne in Embakasi, Proposed Upgrade of Conveyor Belts System of about 5Km at the Port of Mombasa, Proposed Dirty Bulk Terminal handling Fertilizer, Clinker and Coal of total capacity 200,000 metric tonne near the Port of Mombasa. Project Value Kshs. 24Billion. Status: Complete
Key role; Cost Controller in charge of all matters related to cost management, budget review, cost reporting and preparation of cashflow project, Preparation of Capex reports, Assist in external & internal project audit, Assisting in CAPEX reconciliation, Solving contractual claims, Negotiation and review contracts, Valuation of works, Preparation of financial Appraisal, Preparation of Cost management documents
Proposed Bulk LPG Import, Storage and handling facility in Djibouti. Capacity 5000metric tonnes. Project Value Kshs. 3.6Billion. Status: Inception Stage
Roles; Cost Controller: Feasibility Study, Preparation of Cost Estimates and Project Budget, Preparation of Cost Management documents, Budget Presentation
Proposed Bulk LPG Import, Storage and handling facility in Mombasa. Capacity 20,000metric tonnes. Project Value Kshs. 4.5Billion. Status: Complete
Roles; Assistant Project QS: Preparation of Cost Estimates, Preparation of Valuation, Valuation of variations, Cost reporting, Preparation of Bill of Quantities, Documenting all materials requisition and tracking them, maintaining all cost data and documenting and Preparation of Cost Management documents.
Proposed Short Stay Apartments in Mombasa. Five Storey Building. Project Value 80Million.
Roles: Project QS in-charge of taking site measurements, Preparation of valuation, financial appraisal. Attending Site meetings, Contracts Negotiation, Tender valuation and advising on contract awards